大铲湾码头成为华南首家岸电全覆盖的集装箱码头

12月6日,随着船舶岸电建设二期工程项目竣工验收会议顺利召开,大铲湾码头率先实现了100%岸电泊位覆盖率,成为华南首家岸电全覆盖的集装箱码头大铲湾码头船舶岸电建设二期工程项目竣工验收组由深圳市交通运输局、生态环境局、发展和改革委员会、交通运输局宝安管理局、生态环境局宝安管理局、宝安区发展和改革局,大铲湾码头公司、设计单位、施工单位、监理单位代表及行业资深专家代表共同组成

与会专家及代表详细听取、审阅了工程设计、建设、施工、监理等方面的汇报、资料,并实地考察现场后一致同意项目通过竣工验收市交通运输局港航管理处处长董燕泽在会上表示,深圳港是全国具备岸电设施泊位最多的港口市政府近年出台了绿色低碳港口建设补贴资金管理暂行办法等措施,大力支持深圳港船舶岸电项目,希望港口及各相关单位积极推动船舶连接岸电,主动参与绿色港口建设

The participating experts and representatives listened to and reviewed the reports and materials on engineering design, construction, construction and supervision in detail, and agreed that the project passed the completion acceptance after on-site inspection. Dongyanze, director of the port and Waterway Management Office of the Municipal Bureau of transport, said at the meeting that Shenzhen port is the port with the largest number of berths with shore power facilities in the country. The municipal government has introduced measures such as the Interim Measures for the management of subsidy funds for green and low-carbon port construction in recent years, We strongly support the Shenzhen port ship shore power project, and hope that the port and relevant units will actively promote the connection of ships to shore power and actively participate in the construction of green ports

大铲湾岸电二期工程于2019年2月25日正式展开,并于9月底竣工及通过初步验收,中国船级社全程参与见证模拟带载测试并根据测试结果发出实验合格证明文件

测试运营期间,该岸电设施成功为3艘靠港船舶提供岸电,每次持续供电时长均在10小时左右测试期间所有参数均达到设计要求,全面满足船方需求,充分反映了大铲湾岸电系统的稳定性、可靠性及安全性

During the test and operation period, the shore power facility successfully provided shore power for three berthing ships, and the duration of each continuous power supply was about 10 hours. During the test period, all parameters met the design requirements, fully met the needs of the ship, and fully reflected the stability, reliability and safety of the shore power system in Dachan Bay